Moncalieri - the first operation (1998-2003)

1,500,000 sq. m. – the pre-existing area destined to industrial and services sector activities in the boroughs of Moncalieri (1,100,000 sq. m.) and Trofarello (400,000 sq. m.)

5,500- the people employed in 1997 in the industrial areas of Moncalieri (4,250) and Trofarello (1,250)

1,000 million euro- the annual turnover of the companies located in the Borough of Moncalieri alone

650,000 sq. m. – the overall territorial area added to the existing area

14,500,000 euro- the cost of the urbanisation and infrastructure works carried out over 18 months

9,500,000 euro – the public funds obtained for their realisation

70,000 sq. m. – the already operative area dedicated to services for the companies which have taken up location: 2 hotels, restaurants, self-service bars, bank branches, two office centres for integrated logistics, joint surveillance and phone services, postal services, fire prevention and emergency services, small scale associated commerce and crafts, special parking areas

100,000 sq. m. - of parkland with places to relax or do sports in, jogging tracks

350,000 sq. m. - of land for new manufacturing activities

120,000 sq. m. - of covered space for new manufacturing plants

150,000,000 euro – the estimated cost of the entire project: infrastructures, industrial buildings, new service centres

2,000/2,500 – the number of people who will be employed by the new companies locating to the area, counting personnel in transfer and new posts


Trofarello -the second operation (under construction)

350,000 sq. m. – the overall area of territory involved in the new extension

10,500,000 euro – the value of the urbanisation and infrastructure works currently being carried out and to be completed within 18 months

7,100,000 euro – the public funds obtained for their realisation

30,000 sq. m. – the area destined to services for the companies which have taken up location: hotels, restaurants, self-service bars, bank branches, two office centres for integrated logistics, joint surveillance and phone services, postal services, fire prevention and emergency services, small scale associated commerce and crafts, special parking areas

70,000 sq. m. - the area destined for parkland with places to relax or do sports in, jogging tracks

220,000 sq. m. - of land for new manufacturing activities

110,000 sq. m. - of covered space for new manufacturing plants

100,00,000 euro - the estimated cost of the entire project: infrastructures, industrial buildings, new service centres

1,400/1,700 the number of people who will be employed by the new companies locating to the area, counting personnel in transfer and new posts


The new Integrated Services Centre

building with 4 floors above ground
2 stairwells
1,000 sq. m. of covered space
16 easily incorporated real estate units
60 private parking spaces
large adjacent public car park

Infrastructures

First operation: integrated development area of Moncalieri
Urbanisation (direct and indirect) of the extension area. Operations on a total area of 680,000 sq. m. to achieve the total urbanisation of an area of 503,000 sq. m – new turn-off from the ring road – widening of the S.S. 393 with creation of a roundabout at the entrance to the tecnopolo – almost 6 km of new canals, with railway and ring road underpass.

20 September 1997 start of works; 31 May 1999 termination of works

11,840,200 euro’s worth of works , of which 3,792,000 euro for works to ensure the hydro-geological safety of the area (over 32% of the total)

Modification of 220.000 volts electric power line interfering with the land

27 July 1999 start of works; 6 September 1999 termination of works

353,800 euro’s worth of works

Financed by the EEC
Sum financed L. 18,060,000,000 to be made entirely available by December 1999

Tests

15 September 1999 technical-administrative test of the main project

14 June 1999 ANAS/ATIVA technical test of the new turn-off from the ring road

18 July 2000 ANAS technical test of the modification works to the S.S. 393

16 September 1999 technical-administrative test of the secondary project


Handing over of Works and Areas

10 November 1999 handing over of the works in the main project to the Municipality of Moncalieri; 5 November 1999 handing over to the Municipality of Trofarello

2 June 1999 handing over of the new turn-off from the ring road

18 July 2000 handing over of the modification works to the S.S. 393 to the ANAS

25 August 1999 handing over to ENEL of the modification works to the electric power line

Second operation: Integrated Development Area of Trofarello
Urbanisation (direct and indirect) of the extension area. Operations on a total area of 350,000 sq.m. to achieve the total urbanisation of an area of 226,000 sq.m – completion of the turn-off from the ring road – new railway bridge – remaking of over km of water courses to ensure the hydro-geological safety of the area.

13 October 2003 start of works
31 March 2004 forecast date of completion
8,196,000 euro’s worth of works

Financed by the EEC
7.165.558 euro the amount financed