Moncalieri - the first operation (1998-2003)
|
1,500,000 sq. m. – the
pre-existing area destined to industrial and services sector
activities in the boroughs of Moncalieri (1,100,000 sq. m.)
and Trofarello (400,000 sq. m.) |
|
5,500- the people employed
in 1997 in the industrial areas of Moncalieri (4,250) and
Trofarello (1,250) |
|
1,000 million euro- the annual
turnover of the companies located in the Borough of Moncalieri
alone |
|
650,000 sq. m. – the
overall territorial area added to the existing area |
|
14,500,000 euro- the cost
of the urbanisation and infrastructure works carried out over
18 months |
|
9,500,000 euro – the
public funds obtained for their realisation |
|
70,000 sq. m. – the
already operative area dedicated to services for the companies
which have taken up location: 2 hotels, restaurants, self-service
bars, bank branches, two office centres for integrated logistics,
joint surveillance and phone services, postal services, fire
prevention and emergency services, small scale associated
commerce and crafts, special parking areas |
|
100,000 sq. m. - of parkland
with places to relax or do sports in, jogging tracks
|
|
350,000 sq. m. - of land for
new manufacturing activities |
|
120,000 sq. m. - of covered
space for new manufacturing plants |
|
150,000,000 euro – the
estimated cost of the entire project: infrastructures, industrial
buildings, new service centres |
|
2,000/2,500 – the number
of people who will be employed by the new companies locating
to the area, counting personnel in transfer and new posts |
Trofarello -the second operation (under construction)
|
350,000 sq. m. – the
overall area of territory involved in the new extension |
|
10,500,000 euro – the
value of the urbanisation and infrastructure works currently
being carried out and to be completed within 18 months |
|
7,100,000 euro – the
public funds obtained for their realisation |
|
30,000 sq. m. – the
area destined to services for the companies which have taken
up location: hotels, restaurants, self-service bars, bank
branches, two office centres for integrated logistics, joint
surveillance and phone services, postal services, fire prevention
and emergency services, small scale associated commerce and
crafts, special parking areas |
|
70,000 sq. m. - the area destined
for parkland with places to relax or do sports in, jogging
tracks |
|
220,000 sq. m. - of land for
new manufacturing activities |
|
110,000 sq. m. - of covered
space for new manufacturing plants |
|
100,00,000 euro - the estimated
cost of the entire project: infrastructures, industrial buildings,
new service centres |
|
1,400/1,700 the number of
people who will be employed by the new companies locating
to the area, counting personnel in transfer and new posts |
The new Integrated Services Centre
|
building with 4 floors above ground |
|
2 stairwells |
|
1,000 sq. m. of covered space |
|
16 easily incorporated real estate units |
|
60 private parking spaces |
|
large adjacent public car park |
Infrastructures
First operation: integrated development area of Moncalieri
Urbanisation (direct and indirect) of the extension area. Operations
on a total area of 680,000 sq. m. to achieve the total urbanisation
of an area of 503,000 sq. m – new turn-off from the ring road
– widening of the S.S. 393 with creation of a roundabout at
the entrance to the tecnopolo – almost 6 km of new canals,
with railway and ring road underpass.
|
20 September 1997
start of works; 31 May 1999 termination of works |
|
11,840,200 euro’s worth
of works , of which 3,792,000 euro for works to ensure the
hydro-geological safety of the area (over 32% of the total) |
Modification of 220.000 volts electric power line
interfering with the land
|
27 July 1999 start
of works; 6 September 1999 termination of works |
|
353,800 euro’s worth of works |
Financed by the EEC
Sum financed L. 18,060,000,000 to be made entirely available by
December 1999
Tests
|
15 September 1999
technical-administrative test of the main project |
|
14 June 1999 ANAS/ATIVA technical
test of the new turn-off from the ring road |
|
18 July 2000 ANAS technical
test of the modification works to the S.S. 393 |
|
16 September 1999 technical-administrative
test of the secondary project |
Handing over of Works and Areas
|
10 November 1999
handing over of the works in the main project to the Municipality
of Moncalieri; 5 November 1999 handing over to the Municipality
of Trofarello |
|
2 June 1999 handing over of the new turn-off
from the ring road |
|
18 July 2000 handing over
of the modification works to the S.S. 393 to the ANAS |
|
25 August 1999 handing over
to ENEL of the modification works to the electric power line
|
Second operation: Integrated Development Area
of Trofarello
Urbanisation (direct and indirect) of the extension area. Operations
on a total area of 350,000 sq.m. to achieve the total urbanisation
of an area of 226,000 sq.m – completion of the turn-off from
the ring road – new railway bridge – remaking of over
km of water courses to ensure the hydro-geological safety of the
area.
|
13 October 2003 start of works |
|
31 March 2004 forecast date of completion |
|
8,196,000 euro’s worth of works |
Financed by the EEC
7.165.558 euro the amount financed
|